What actually changed when NZS 3910 was updated to the 2023 edition?
Three things that matter in practice: the old single Engineer role was split into a Contract Administrator and an Independent Certifier, a new Target Price pricing option was added alongside the traditional structures, and a specific environmental compliance clause was introduced. If you’re still running a project the way you would have under the previous edition, those three changes are where your process is most likely out of date.
The Engineer role doesn’t exist as a single position anymore
Under earlier editions, one Engineer represented the principal and also had to certify valuations, variations and extensions of time fairly and independently — a position that always carried some tension between the two functions. NZS 3910:2023 splits it in two: a Contract Administrator, who represents the principal and issues day-to-day instructions, and a separate Independent Certifier, who is required to act fairly, impartially and independently when valuing work, assessing variations, and granting extensions of time.
For a project manager used to the old structure, the practical adjustment is making sure everyone on the project, including subcontractors, understands which of the two roles they’re actually dealing with on a given issue. Directing a certification question to the Contract Administrator, or an instruction query to the Independent Certifier, is a straightforward mistake that wastes time and can complicate a dispute if it happens repeatedly.
A genuine third pricing option, not just lump sum or measure and value
NZS 3910:2023 added a Target Price option to the traditional lump-sum and measure-and-value structures. It suits a project where the scope is reasonably well defined but there’s value in sharing cost outcomes between principal and contractor rather than fixing a single price up front. It isn’t a replacement for the other two structures — it’s a genuine third option that needs to be chosen deliberately, based on how well-defined the scope actually is, not defaulted to because it’s new.
A real environmental clause, narrower than it sounds
NZS 3910:2023 introduced a specific “protection of the environment” clause requiring the contractor to take all reasonably practicable steps to avoid an unlawful discharge, a noise-limit breach, a resource consent breach, or conduct that could expose the project to prosecution during the works. It’s a targeted compliance obligation, not a broad sustainability mandate, and it needs to be built into the site management plan and monitored the same way any other contractual obligation would be, rather than treated as a values statement.
What this means for how a project should actually be run
None of these three changes rewrites how a construction project is managed day to day — the phases, the documentation discipline, and the need for clear communication are unchanged. What they do is shift specific decisions a project manager needs to get right: confirming which certifying role is being engaged on any given issue, choosing a pricing structure that genuinely fits the project’s scope rather than defaulting to habit, and treating the environmental clause as an enforceable term with its own monitoring, not background compliance. A team still working from 2013-edition habits is the team most likely to get one of these three details wrong.
Getting the transition right
The contract itself does the structural work. What determines whether a project actually benefits from the 2023 changes is whether the people running it understand exactly what’s different, and adjust their process accordingly rather than carrying old habits into a new edition of the contract.
Common questions
What are the main changes in the NZS 3910:2023 revision?
Three changes matter most in practice: the old single Engineer role has been split into a Contract Administrator (who represents the principal and issues instructions) and an Independent Certifier (who values work, assesses variations and grants extensions of time fairly and independently); a new Target Price pricing option was added alongside lump sum and measure and value; and a specific environmental compliance clause was introduced requiring the contractor to avoid unlawful discharges, noise breaches and consent breaches.
Does NZS 3910:2023 include new sustainability or digital/BIM requirements?
Not in the broad way sometimes described. The 2023 revision introduced a specific, narrow environmental compliance clause covering discharges, noise and consent breaches — it isn’t a general sustainability mandate. There is no digital integration or Building Information Modelling (BIM) provision in the 2023 revision.
Still working from the old NZS 3910 playbook?
Get your contract administration and certification roles set up correctly under the current edition. Tell us about your project.
© 2026 Aamsko. All rights reserved. Level 1, 30 Broadway, Newmarket, Auckland 1023, New Zealand.



Level 1, 30 Broadway