What caused the water ingress at 128 Broadway?

Failed jamb and head flashings on the aluminium-framed windows let water travel behind the cladding on two elevations, tracking down through the timber framing before it ever showed up inside a tenancy. By the time staining appeared on Levels 3 and 4, the moisture had already been moving through the wall for some time — which is why the fix had to treat the building envelope as one connected system, not a set of isolated leaks.

The problem: a landmark Newmarket office building, quietly failing

128 Broadway is one of Newmarket’s more prominent commercial office buildings, home to a mix of law firms, consultancies and other professional tenants. The Body Corporate came to Aamsko after water staining, warped finishes and intermittent leaks — worst during wind-driven rain — started affecting multiple levels. Leaks that only show up in certain weather are hard to trace and easy to underestimate; the Body Corporate’s instinct that patch repairs were no longer the answer turned out to be correct.

Water wasn’t entering at one point and staying there. It was tracking down from higher levels, concealed behind cladding and framing, before finally showing up inside a tenancy two floors down.

The approach: forensic diagnosis before any design work

Aamsko’s building surveyors carried out a full weathertightness investigation — physical inspection, thermal imaging, invasive moisture testing and AAMA 511 spray testing, the forensic standard that recreates real-world weather conditions in a controlled way to see exactly how water moves through a building assembly. That testing found two distinct failure patterns:

  • North and west elevations: deteriorated jamb flashings on the large aluminium-framed windows had let moisture travel behind the Eterpan fibre-cement cladding and down through the timber framing.
  • East elevation: head flashings that had been poorly designed and installed were collecting water at the joinery head and pushing it through unsealed cladding interfaces — made worse by makeshift drainage holes drilled into the joinery in an earlier attempt to manage the leaks, which only created new entry points.
Annotated AAMA 511 findings drawing of the western office window section at 128 Broadway, showing an undersized window stool angle and missing building paper
Annotated cross-section drawing of the northern façade at 128 Broadway showing wet cracking and rust risk to steel reinforcement

Internally, the damage matched the diagnosis: decaying framing, stained linings, carbonation on some concrete beams from sustained damp, and mould and standing water in the fire-escape stairwell and toilet areas. This was a textbook leaky building — but 128 Broadway is also a fully tenanted, multi-storey commercial building operating in the middle of Newmarket, which meant the remediation had to be precisely detailed and workable around a building that couldn’t simply close.

Annotated wall cavity section drawing of the eastern toilet area at 128 Broadway showing rotten timber and water tracking
Annotated window section drawing of the eastern fire-escape stairwell at 128 Broadway showing fungal growth and a missing cill flashing

The remediation: three packages, one system

Aamsko’s remediation design split the work into three packages, each addressing a different failure mode on a different part of the building, specified with real, named products rather than a generic scope:

2building elevations diagnosed with distinct failure modes
3remediation packages specified, one per problem
AAMA 511forensic testing standard used to trace the ingress

North and west elevations. Custom-fabricated aluminium jamb flashings over every vertical junction, supported with SikaHyflex®-250 Facade and Sika® SealTape B for long-life, high-movement seals between joinery and cladding, plus Tank-It Liquid Flashing to window stools and sills for a seamless barrier beneath the new flashings. Degraded silicone joints were removed and replaced with new backing rod and sealant.

East elevation. A retrofit overflashing pressure-bar system, mechanically fixed over the existing head flashings to create a sealed, compressive barrier, with all external sealant joints replaced using high-performance, movement-capable façade sealants and SealTape B at every junction. This achieved the waterproofing performance of a full window replacement without the disruption of one.

Building-wide elastomeric coating. Localised repairs only go so far if the cladding isn’t treated as a whole system. Aamsko specified crack repair with Sikaflex® AT Facade and backing rod for anything over 5mm, substrate preparation with Granoprime, and two full coats of Wattyl GranoShield Matt — a flexible, breathable, UV-resistant coating that bridges hairline cracks and moves with the building rather than cracking again with it.

Contracting and oversight

Aamsko delivered a full Statement of Work, priced using QV CostBuilder, and recommended the project be run under an NEC3 construction contract for clarity on contractor obligations, programme and dispute resolution. The Body Corporate could proceed with Aamsko’s preferred contractor or run a competitive tender managed entirely by Aamsko — either way, Aamsko stayed involved to check the remediation design was actually being built as specified, including installation guides, sequencing plans and material specifications for every part of the building, with trust-held project funds and real-time reporting back to the Body Corporate.

The result

The remediation design gives the Body Corporate a costed, buildable path to a dry building — not a diagnostic report to interpret on its own. Treating 128 Broadway’s envelope as one connected system, rather than three unrelated leak complaints, is what turns a recurring maintenance problem into a long-term fix that protects the asset’s value rather than deferring the cost.